FY 2023 Slurry Seal and Crack Seal Program

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

      Project Location

      The project location for Slurry Seal Installation is in Maintenance District 1 through 3. The project location for Crack Sealing is in various districts across the City. Please click HERE to view the project location map.

      Scope of Work

      The scope of the work for this project generally includes:

      • Selective removal/reconstruction of deteriorated pavement and placement of asphalt concrete pavement
      • Selective removal/reconstruction of Portland cement concrete pavement and placement of Portland cement concrete pavement
      • Asphalt concrete skin patching of deteriorated asphalt concrete pavement
      • Application of emulsion aggregate slurry (Slurry Seal Type II)
      • Application of crack sealing material
      • Removal and replacement of existing traffic striping and pavement marking
      • Selective removal, repair and reconstruction of damaged curbs, gutters, sidewalks, driveways, cross gutters, and alley aprons, including disposal of asphalt and Portland cement concrete pavements

      Phase

      The Project is currently in construction.

      Construction Schedule

      Construction is scheduled from April 2024 thru August 2024 barring unforeseen circumstances.

      Construction Updates

      June 14 – July 15: Contractor is working on tree planting, asphalt repair, crack seal and slurry seal installation.

       June 17 and 18: Tree Installation at various streets.

      June 20-28: Asphalt Repair, Crack Sealing, and Tree Installation various locations

      June 24 – July 2: Striping Removal and Surface Preparation for Slurry Seal Installation

       FY 2023 Slurry Phasing ExhibitPDF

      July 8 – Slurry Seal Installation Affected Streets:

      • Windsor Road between Glendale Avenue and Granada Street (North Side)
      • Windsor Road between Porter Street and Verdugo Road (North Side)
      • Windsor Road between Mid-Block (E. of Verdugo) and E’ly Terminus (North Side)
      • Garfield Avenue between Verdugo Road and Mid-Block (E. of Verdugo) (North Side)
      • Cambridge Drive between Cornell Drive and Dartmouth Drive
      • Wellesley Drive between Dartmouth Drive and Columbia Drive
      • Yale Drive between Adams Street and Scofield Drive
      • Stanford Drive between Berkeley Drive and Vanderbilt Place
      • Loma Crest Street between Marion Drive and N’ly Terminus
      • Marion Drive between Scenic Drive and Oberlin Drive
      • Scenic Drive between Corona Drive and E’ly Terminus
      • Palmer Avenue between Mid-Block (N. of Oberlin Drive) and E’ly City Limit
      • Romulus Drive between Oberlin Drive and E’ly City Limit
      • Park Avenue between Tyler Street and Marion Drive

       July 9 – Slurry Seal Installation Affected Streets:

      • Windsor Road between Glendale Avenue and Granada Street (South Side)
      • Windsor Road between Porter Street and Verdugo Road (South Side)
      • Windsor Road between Mid-Block (E. of Verdugo) to E’ly Terminus (South Side)
      • Garfield Avenue between Verdugo Road and Mid-Block (E. of Verdugo) (South Side)
      • Roads End Street between Glendale Avenue to Mid-Block (W. of Colby Drive)
      • Princeton Drive between Adams Street and Marion Drive
      • Corona Drive between Mid-Block (1400 Corona) and Scenic Drive
      • Vanderbilt Place between Stanford Drive and Marion Drive
      • Oberlin Drive between Palmer Avenue and Marion Drive
      • Marion Drive between Palmer Avenue and Romulus Drive
      • Park Avenue between Adams Street and Tyler Street (North Side)

       July 10 – Slurry Seal Installation Affected Streets:

      • Windsor Road between Granada Street and Mid-Block (W. of Adams Street) (South Side)
      • Windsor Road between Adams Street and Chevy Chase Drive (South Side)
      • Windsor Road between Verdugo Road and Mid-Block (E. of Verdugo) (South Side)
      • Garfield Avenue between Mid-Block (E. of Verdugo) and E’ly Terminus (South Side)
      • Elk Avenue between Central Avenue and Brand Boulevard (Center Lane)
      • Magnolia Avenue between Central Avenue and Brand Boulevard (Center Lane)
      • Tyler Street between Chevy Chase Drive and Park Avenue
      • Corona Drive between Vista Superba Drive and Mid-Block (1400 Corona)
      • Marion Drive between Scenic Drive and Loma Crest Street
      • Scofield Drive between Adams Street and Princeton Drive
      • Palmer Avenue between Marion Drive and Oberlin Drive
      • Dartmouth Drive between Cornell Drive and Adams Street
      • Columbia Drive between Cornell Drive and Mid-Block (1500 Columbia)

       July 11 – Slurry Seal Installation Affected Streets:

      • Windsor Road between Granada Street and Mid-Block (W. of Adams Street) (North Side)
      • Windsor Road between Adams Street and Chevy Chase Drive (North Side)
      • Windsor Road between Verdugo Road and Mid-Block (E. of Verdugo) (North Side)
      • Garfield Avenue between Mid-Block (E. of Verdugo) and E’ly Terminus (North Side)
      • Heminger Street between Glendale Avenue and Colby Drive
      • Elk Avenue between Central Avenue and Brand Boulevard (North and South Parking Lanes)
      • Magnolia Avenue between Central Avenue and Brand Boulevard (North and South Parking Lanes)
      • Louise Street between Windsor Road and Maple Street
      • Park Avenue between Adams Street and Tyler Street (South Side)
      • Vincent Way between Adams Street and N’ly Terminus

       July 12 – Slurry Seal Installation Affected Streets:

      • Windsor Road between Adams Street and Mid-Block (W. of Adams Street) (North Side)
      • Windsor Road between Chevy Chase Drive and Porter Street (North Side)
      • Columbia Drive between Mid-Block (1500 Columbia) to Wellesley Drive
      • Cornell Drive between Crescent Drive and Adams Street
      • Berkeley Drive between Adams Street and Stanford Drive
      • Marion Drive between Loma Crest Street and City Limit
      • Marion Drive between Palmer Avenue and Oberlin Drive
      • Oberlin Drive between Romulus Drive and Palmer Avenue
      • Vista Superba Drive between Corona Drive and S’ly Terminus
      • Tyler Street between Palmer Avenue and Park Avenue

       July 15 – Slurry Seal Installation Affected Streets:

      • Windsor Road between Adams Street and Mid-Block (W. of Adams Street) (South Side)
      • Windsor Road between Chevy Chase Drive and Porter Street (South Side)
      • Romulus Drive between Tyler Street and Oberlin Drive
      • Crescent Drive between Adams Street and Cornell Drive
      • Tyler Street between Palmer Avenue and Green Street
      • Palmer Avenue between Oberlin Drive and Mid-Block (N. of Oberlin Drive)
      • Berkeley Drive between Stanford Drive and Princeton Drive
      • Scenic Drive between Marion Drive and E’ly Terminus
      • Stanford Drive between Adams Street and Vanderbilt Place
      • Columbia Drive between Wellesley Drive and Adams Street

       Traffic Impacts

      Travel lanes in both directions may be closed intermittently between 7:00 AM – 4:00 PM (excludes weekends) on the following streets:

      • Windsor Road between Glendale Avenue and E’ly Terminus (7/8/2024 thru 7/15/2024)
      • Garfield Avenue between Verdugo Road and E’ly Terminus (7/8/2024 thru 7/11/2024)
      • Elk Avenue between Central Avenue and Brand Boulevard (7/10/2024 thru 7/11/2024)
      • Magnolia Avenue between Central Avenue and Brand Boulevard (7/10/2024 thru 7/11/2024)
      • Park Avenue between Adams Street and Marion Drive (7/8/2024, 7/9/2024, 7/11/2024)
      • Loma Crest Street between Marion Drive and N’ly Terminus (7/8/2024)
      • Yale Drive between Adams Street and Scofield Drive (7/8/2024)
      • Cambridge Drive between Cornell Drive and Dartmouth Drive (7/8/2024)
      • Wellesley Drive between Dartmouth Drive and Columbia Drive (7/8/2024)
      • Columbia Drive between Cornell Drive and Adams Street (7/10/2024, 7/12/2024,  7/15/2024)
      • Tyler Street between Green Street and Chevy Chase Drive (7/10/2024, 7/12/2024, 7/15/2024)
      • Roads End Street between Glendale Avenue and Colby Drive (7/9/2024)
      • Heminger Street between Glendale Avenue and Colby Drive (7/11/2024)
      • Louise Street between Windsor Road and Maple Street (7/11/2024)
      • Vincent Way between Adams Street and N’ly Terminus (7/11/2024)
      • Dartmouth Drive between Cornell Drive and Adams Street (7/10/2024)
      • Cornell Drive between Crescent Drive and Adams Street (7/12/2024)
      • Crescent Drive between Adams Street and Cornell Drive (7/15/2024)
      • Scofield Drive between Adams Street and Princeton Drive (7/10/2024)
      • Vanderbilt Place between Marion Drive and Stanford Drive (7/9/2024)
      • Stanford Drive between Adams Street and Berkeley Drive (7/8/2024 and 7/15/2024)
      • Romulus Drive between Tyler Street and City Limit (7/8/2024 and 7/15/2024)
      • Vista Superba Drive between Corona Drive and S’ly Terminus (7/12/2024)
      • Corona Drive between Vista Superba Drive and Scenic Drive (7/9/2024 and 7/11/2024)
      • Palmer Avenue between Tyler Street and City Limit (7/8/2024, 7/11/2024, and 7/15/2024)
      • Marion Drive between Romulus Drive to City Limit (7/8/2024, 7/9/2024,7/10/2024, and 7/12/2024)
      • Oberlin Drive between Romulus Drive and Marion Drive (7/9/2024 and 7/12/2024)
      • Scenic Drive between Marion Drive and E’ly Terminus (7/8/2024 and 7/15/2024)
      • Berkeley Drive between Adams Street and Princeton Drive (7/12/2024 and 7/15/2024)
      • Princeton Drive between Adams Street and Marion Drive (7/9/2024)

         Construction Photos

       slurry seal 2

      slurry seal 1

      Community Meeting

       FY23Slurry Notification 3-14-23

      When: Tuesday, March 14, 2023

      Where: Glendale City Hall Council Chambers (613 E. Broadway, Glendale CA 91206)

      Time: 6:00 PM

      Watch this meeting on YouTube

      Contact Information

      • Public Works Engineering: (818) 937-8326
      • Public Works Project Manager: Rustom Tavitian, P.E.; RTavitian@glendaleca.gov