Interstate 210 Freeway Soundwall Construction Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Scope of Work

  • The project scope includes preparing the Project Study Report - Project Report/Noise Barrier Sound Study Report and Preliminary Environmental Assessment Report as a prerequisite for determining feasibility and constructability of the soundwalls and completing a subsequent design.

Phase

Project Status 

  • The project is in a pre-design phase. The preliminary soundwall layout started in July 2020. A field scoping to identify the soundwall locations will start in mid-October 2020. 

Project Schedule

 Project Schedule  Start  Complete
Pre-design Phase - Project Study Report (PSR-PR_ Preparation by Caltrans  July 2020  December 2021
Design Phase - Plans, Specifications, Estimate (PS&E) Preparation  TBD  TBD
Right-of-Way (ROW) Acquisitions  TBD  TBD
Construction Phase  TBD  TBD

 

 Traffic Impacts

  • Check back at the start of the project!

Project Location

  • The 210 Freeway Soundwall Construction Project will take place along the 210 Freeway between Lowell Avenue and Pennsylvania Avenue, in both the east and west bound directions.
  • Click here for Project Location

Construction Schedule

  • Check back at the start of the project!

Community Meetings

  • Click here to view the virtual community meeting notification

When: Monday, December 13, 2021 
Time: 6:00PM
Link: Shown in document attached above

  • Click here to access the recorded virtual meeting
  • Click here to view the Responses to Questions/Comments Received During Virtual Community Meeting on 12/13/2021

Contact Information

  • Public Works Engineering, (818) 548-3945
  • Public Works Project Manager, Armen Avazian Email